Project Update
Steel Pile Installation Begins at 3070 Bailey Ave
06/17/2025

A project update from our Construction Team:
It all starts with a solid foundation! Steel pile installation has begun at 3070 Bailey Avenue.
What’s a steel pile, you ask? They are steel columns that are driven into the bedrock to help support the load of the building.
A total of 96 steel piles are needed for this project, with each one taking 10-15 minutes to drive fully into the ground.
What’s next for the project? Excavation for the elevator pit. Stay tuned!